The World Bank has raised concerns over delays in compensating landowners affected by the construction of the 740-kilometre Isiolo-Mandera Highway, warning that the setbacks are adding billions of shillings to the project’s costs.

In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport Cabinet Secretary Davis Chirchir and Lands Cabinet Secretary Alice Wahome, the bank’s Kenya Division Director, Qimiao Fan, said contractors were still unable to access some sections of the road because compensation had not been completed.

Fan said the bank had made funds available for compensation since 2024, but the process only started in November 2025. Payments have so far been limited to the Isiolo-Modogashe section.

The delays have left some construction sites partially inaccessible, affecting work schedules and exposing the project to additional costs.

The World Bank estimates that every month of restricted access across the six active road contracts adds about KSh1 billion in recurring expenses. These include security, supervision, site facilities, idle equipment and personnel costs, as well as price increases.

A further KSh207.5 million is incurred monthly through the demobilisation and remobilisation of equipment.
Also, the bank expressed worry over the number of affected landowners who have already been compensated. Of the 1,669 people who were affected by the project, only 1,281 have been compensated according to the letter.

On the Isiolo-Kulamawe stretch, the compensation had reached KSh456 million. But the bank warned that any delays on this stretch would put the project under the risk of incurring additional monthly expenses of KSh536 million.

The Wajir-Tarbaj-Kotulo stretch too has been experiencing delays. Although it is expected to have its compensation done by November 2026, the bank expects it to lead to additional monthly costs of KSh421 million.

On the Kotulo-Kobo-Eluaki stretch, the projected additional monthly cost is KSh243 million.

According to the bank, the project may face increased costs due to contractual risks due to the delays.

The Isiolo-Mandera Highway is being built under the Horn of Africa Gateway Development Project funded by the World Bank.

According to the latest report on October 26, the project was 60 per cent complete. Initially expected to be completed by January 2028, the completion date has been pushed back to 2030.