Home KENYA Mbadi Rules Out Cancelling CRBC Contracts Over World Bank Report

Mbadi Rules Out Cancelling CRBC Contracts Over World Bank Report

0
46

Treasury Cabinet Secretary John Mbadi has ruled out cancelling government contracts awarded to China Roads and Bridges Corporation (CRBC), saying the World Bank’s report on corruption and costly projects did not directly implicate the Chinese contractor.

Mbadi said the government would not terminate contracts simply because questions had been raised about the cost of some infrastructure projects.

Speaking during an interview on Citizen TV on Tuesday, November 17, the CS said each project should be examined separately to establish what caused the high construction costs.

He pointed to the Standard Gauge Railway (SGR), saying the cost of the line from Mombasa to Naivasha needed closer examination, including the money spent on land compensation.

“For me, I delink these projects and deal with them independently. On the SGR from Mombasa to Naivasha, yes, there are questions that probably we could have spent less. But we need to dig deep and find out what would have led to escalation costs. One of the reasons for the escalation is usually about land compensation and not the contractor,” Mbadi said.

The Treasury CS was responding to concerns raised in the World Bank’s Kenya Economic Update report released on November 4, which questioned the cost of major infrastructure projects, particularly the SGR.

The report put the construction cost of Kenya’s Mombasa-Nairobi SGR at KSh988 million per kilometre.

This was higher than the KSh741 million per kilometre spent on Tanzania’s electrified Dar es Salaam-Dodoma railway and KSh689 million per kilometre for the electrified Djibouti-Addis Ababa line.

The World Bank estimated that Kenya could have saved up to KSh116 billion had the railway been built at the same cost per kilometre as Tanzania’s line.

The findings renewed calls for the government to review contracts awarded to CRBC, which has secured several major infrastructure projects in Kenya.

Among them are the Rironi-Mau Summit Highway and the KSh154 billion Jomo Kenyatta International Airport expansion project.

However, Mbadi argued that cancelling the contracts would expose the government to legal battles, particularly if the contractor had followed the required procurement procedures.

He said CRBC had not been blacklisted and maintained that the company should not be denied contracts if it follows the law and wins a tender.

“CRBC has not been blacklisted, and they won the contract, for example, the JKIA expansion. If we cancel the tenders, they can take us to court and win. So I don’t see why we would not award them the tender even tomorrow if they apply and win,” he said.

Mbadi also singled out the Rironi-Mau Summit Highway, saying he had not seen anything questionable about the procurement process, although the Auditor-General could raise concerns during an audit.

“For the Rironi-Mau Summit project, I have not seen anything that would be questionable; the Auditor General may highlight. But as far as whether the procurement process was followed, I have no doubt it was followed,” he added.

The CS urged Kenyans to read the World Bank report and examine the issues raised, saying the government needed to establish what drove up the cost of the projects rather than rush to cancel contracts.

NO COMMENTS